Of course the method statement allows it. I have just finished 3 roof jobs and done the majority of it on my own, just brought staff in as and wen I needed
Anything is permitted as long as it's done safely, and u put it in ur rams. If there was a problem the job would of been stopped.
The worst thing about doing big jobs like this is wen u r on the roof/cherrypicker or whatever access ur using, and suton goes wrong at the van, it can take a while to go sort a 2 second problem and then get back to were u was.
So what happens if you need urgent help for whatever reason. How is that covered when working alone in your RAMS Matt?
What does urgent help consist of ??
Let's be honest an not daft, if u assess the job and see that there could be problems then u allow for them.
But this is ciu an no matter how u word it, u guna get pulled apart, rob only just came back an he's prob thinking wot for.
No hypo permitted on this site, so only things that can go wrong r as follows. ( all work had to go through h&s )
Machine runs out of petrol
A
Go the garage
Hose may burst
A
Replace hose by ringing Rutland pumps
Building falls down due to earthquake
A
If still alive have an early dart go to a&e get checked out
Ok so 1 things did go wrong on the job over the last 6 weeks, my unloader on jet wash worked it's way loose an I had a leak, posted pic on here and Ben and Chris pointed me in the right direction.
Disaster over