Hi Huw/Colin
You cannot create jobs that span more than one day at the moment, but I'm planning to add this at some point, (along with appointments for specific times).
In the meantime, you could set the job with a Time Required for a full day, then add this job on each of the days it takes, but mark all but the first 'Not Done'. That way, you have an indication on the planner that multiple days are required, without the job appearing more than once in your accounts/invoices... Does that make sense?
Darran: You can plan ahead as far as you like manually, but auto scheduling only works one job in advance. I'm going to be extending this soon so that you can see where work will be much further ahead, e.g. 10 jobs which would give you 40 weeks forward load on a four weekly round.
Thanks
Chris.