Hi Joe,
The problem is that you have told the system that the next due date can ONLY be on certain days. In this instance if you are booking a job that was due say 28th Nov but you only mananged to do this today 3rd Dec, the system has schedule forward 4 weeks which works out Thursday 31st Dec. Since you have told the system to only do this job on a monday it has rolled forward to the 4th Jan.
There are a few options:
1) You can change the roll direction to forwards(default) or backwards. In the case above it would then schedule for 28th Dec.
2) Take off the day restrictions and let the system just schedule 4 weeks from the day you did the job
3) Change the system to shedule 4 weeks from due date rather than cleaned date.
4) If you really want to keep the work in weekly order the instead of using the daily restrictions then you can use the week in month instead
Hope that makes sense, let me know if you need any more help
Thanks
Ian