need an answer quick please
« on: May 22, 2007, 09:30:13 pm »
hi people

can you give an answer quick cos i need to get this quote in the post tommorrow,  does this sound right to you

builders clean at new built school, (dont know size) its sort of big
mainly dust and windows to do,
4 guys
7hrs a day
8 days
£12 an hr each charging but only paying them £6
and i work it out as £2688

please answer back quick please

thanx jonny

let castle take the hassle




Jake

  • Posts: 348
Re: need an answer quick please
« Reply #1 on: May 22, 2007, 09:48:09 pm »
Jonny

Don't know if anyone will be able to comment on your prices if the only information they have is 'it's sort of big'.

Is it a brand new secondary school or an extension to a primary school? You really should find out more mate.

                              Regards...........Jake
Exeter, Devon

Jonny jones

  • Posts: 387
Re: need an answer quick please
« Reply #2 on: May 22, 2007, 10:06:44 pm »
been there today had look around couldnt tell you haw big but do you think that the hrly rate is ok or too high,  i know it will take that long to clean and its a newly built primary school

martin19842

  • Posts: 1945
Re: need an answer quick please
« Reply #3 on: May 22, 2007, 10:18:41 pm »
hi there

floor cverings??  wil they be in or not  ?? [protected or not ??  if theyare in what are they??

you should have at least looked at some plans to get an idea of size.

high level access equipment ??

i would be nearer £3200, but i wouldnt even go foa a quote without the above answered.

regards

martin


Jonny jones

  • Posts: 387
Re: need an answer quick please
« Reply #4 on: May 22, 2007, 10:29:42 pm »
got ladders for the high level because thats no problem only one big hall,
floor coverings mostly altro and vinyl, some carpets but nothing much.
and yes they asure me they will be covered

im writing the quote now becuse could be in there in two weeks doing the first half then 2 weeks later doing the rest

should put down in the quote that if its done quicker there will be a discount, or just leave that bit out and hope i gain a couple opf quid

thanx jonny

mxg

  • Posts: 187
Re: need an answer quick please
« Reply #5 on: May 22, 2007, 11:40:33 pm »
Johny

If its done quicker only give a discount if they agree to pay more if it takes longer. Wont happen so discount doesn't come in to it.

Might be worth building in some contingency for the things that will go wrong/take longer than planned